15.9 billions to send electricity to Stamigold mine

15.9 billions to send electricity to Stamigold mine

15.9 billions to send electricity to Stamigold mine: Know six important facts about the 15.9 billion spent on Stamigold Mine Electricity.

> The project was completed on April 20, 2023 and STAMIGOLD officially started using electricity from the national grid on April 26, 2023.

> The power line built is 33 kilowatts.

> The route is 105 kilometers from the Mpomvu – Geita power receiving station.

> The construction involved the electricity transmission line as well as STAMIGOLD’s electricity receiving and cooling station.

> The station is built with two transformers with a capacity of 10 MVA each, and two transformers of 2.5 MVA

> District Head of Biharamulo ACP. Advera Bulimba has called on investors to invest in the District due to the presence of guaranteed electricity.